In summer 2015, Peterburggaz implemented a project involving the construction of a 12-bar transfer line from the Southern Power gas plant to the Pulkovo Highway. Vexve’s underground DN 800 ball valves were installed on the transfer line. Gas valves manufactured by Vexve are Gazsert-approved and were comprehensively inspected before installation. After testing, Vexve's partner, Aviton, completed the gas insulation for the valves.
Industry | Energy distribution |
Customer | Peterburggaz |
Country | Russia |
City | St. Petersburg |
Project | Transfer line from gas plant to highway |
When | 2015 |
Application | Gas |